On behalf of our client, Chesterfield Borough Council, Ipsum (UK) acted as Principal Contractor during the remedial works to a residential property.
Works to the property included the partial re-build of the gable elevation, installation of remedial wall ties, re-pointing to the entire property, and the installation of an aco drain system to the properties side entrance alleyway.
Following our Structural Engineers design, we re-built the gable elevation and installed structural straps to both the roof rafters and ceiling.
The property was tenanted throughout the works, so extra consideration was taken to remain flexible and adapt our programme to suit the working patterns of the tenants. Our Tenant Liaison Officer communicated scheduled works ahead of time with the tenants to ensure minimal disruption.
Work was completed ahead of schedule and both the tenant and client are delighted with the outcome of the project.